BHPV Merged with BHEL; Becomes Seventeenth Unit of BHEL

BHEL wins order for 206 MW Hydro Electric Project in Punjab

New Delhi, February 26: In the face of stiff international competition, Bharat Heavy Electricals Limited (BHEL) has secured a prestigious contract for setting up a 206 MW Hydro Electric Project (HEP) in the state of Punjab. Significantly, this is the first major order for electro-mechanical equipment, to be finalised by a Govt. utility company in the current financial year, in the hydro sector.Valued at Rs.321 Crore, the order for setting up of Hydro Generating sets and associated Electro-Mechanical works for the 206 MW Shahpurkandi HEP has been placed on BHEL by Punjab State Power Corporation Limited (PSPCL), as its offer was found techno-economically the best.

Notably, the bids for the contract were invited by PSPCL through a Global E-tendering process. With this order, the customer has once again reposed confidence in BHEL’s proven technological excellence and capability in executing such hydro projects.

Located in Gurdaspur district of Punjab, in the plains near the Punjab and J&K border, the project shall be constructed on the canal from Shahpurkandi Barrage to Madhopur headworks, downstream of the existing Ranjit Sagar Dam. The water released by Ranjit Sagar Dam shall be utilised for generating power from this project.

The project comprises seven hydro generating sets located in two Power Houses viz. Power House-I (3×33 MW) and Power House-II (3×33 MW + 1×8 MW). BHEL’s scope of work in the contract envisages design, manufacture, supply, installation and commissioning of hydro generating sets and associated electro mechanical works.

While the hydro generating sets shall be supplied by BHEL’s Bhopal unit, the transformers and Control & Monitoring system will be supplied by the company’s Jhansi unit and Electronics Division, Bangalore, respectively. The erection & commissioning of the equipment shall be carried out by BHEL’s Power Sector – Northern Region (PSNR).

For PSPCL, BHEL is also presently executing the electro-mechanical works for the 2×9 MW Mukerian HEP, wherein bulb turbine generating sets are being supplied. Significantly, BHEL has a share of 90% in the present hydro generating capacity of 1,145 MW of PSPCL.